Case 02 / Software

Handover Tracking System

A tracking system I designed and built to manage the full handover scope of 381 bundles. It shows the stage of every bundle, the party it is waiting on, and the time elapsed against governance. It has since been adopted across the project team.

Role
Concept, design and development
Build time
480 hours
Used by
The wider project team, Al Masjid Al Haram Expansion
Scope
381 bundles
Built with
HTML, JavaScript, Excel import and export, Claude API

How it started

  1. 01 / The problemA very large scope.

    When I took over the handover work, I saw how big the package was: hundreds of bundles, each moving through several parties and review steps. Following that in separate files was not going to hold.

  2. 02 / The ideaOne system to follow it all.

    I designed and built a tracker for myself, with the review sequence and agreed durations built in, so every bundle shows its stage, its owner and its delay.

  3. 03 / The resultIt became the team's tool.

    Other people saw it working and adopted it. It was then rolled out to the rest of the team, who now follow their bundles in it.

The review chain it follows

Every bundle moves through the same sequence of notifications, reviews and site steps, each with a governance duration. The tracker holds those durations, so a delay shows up as days over governance instead of a feeling that something is late.

MOFNotificationstart
MOFHLGA issued3 days
AuthorityReply to contractor2 days
ContractorSite visit1 day
AuthoritySite observation report4 days
AuthorityReply to contractor2 days
ContractorApprove or rejectdecision

What it does

  • All bundles in one list, filterable by status, zone and report type (HLGA or site observation).
  • Bulk update from Excel. Drop the latest status file and every bundle updates at once.
  • Single-bundle update with a new status, a decision owner and a note.
  • Email parsing. Paste the text of an email and the app proposes the bundle changes; the user confirms them.
  • Follow-up view by month and notification date, with counts of late, rejected and signed bundles.
  • Rejected bundles and bundle notes kept in their own views.
  • Reports. Status distribution, completion rate, work by zone and a printable status report.
  • Acceptance minutes and documents tracked alongside each bundle, with Excel export of everything.

Screens

Bundle follow-up
01Bundle follow-up

Totals on top: bundles, finished stages, pending, accepted and rejected. Below, each row is a bundle and every review step shows its date, who holds it, and how many days it is late. Red is overdue, green is done.

Overview matrix
02Overview matrix

All bundles against all document types, with the count of open comments on each item.

Bundle notes
03Bundle notes

Review notes and required items tracked per bundle, ticked off as each one is closed, with a count of how many are done.

Document review
04Document review

The document set each bundle must carry, with accepted and open items marked per document type.

Bundle names and codes are blurred on every screen. Click a screen to enlarge it.

The sequence above is shown with roles, not names. Durations are the agreed standards used in the tracker. Screenshots are from the working application; bundle names and codes are blurred.