The Haram handover, day by day
I designed and built the Power BI dashboard that follows the handover work, from the first idea to the finished pages. It measures cycle times across the bundles against governance, and is reported to the Ministry of Finance as program owner.
I saw where the time was going, and built the way to show it.
- 1The idea
Measure every step of every bundle against its agreed duration, so the delays can be seen.
- 2The build
I designed and built every page in Power BI myself: measures, charts and layout.
- 3The use
The pages became the basis for reporting handover progress and delays to the Ministry of Finance.
The dashboard, page by page
What changed
- Shorter waits. Once every wait was visible, the time bundles spent waiting between steps came down.
- Pressure from day one. We follow up with the contractor on a single day of delay, instead of discovering it weeks later.
- Strong answers to claims. The dated record of every step lets us respond to the contractor's claims with evidence.
- Better negotiation. When the contractor is the one running late, we negotiate with the numbers in hand.
Finding
Waiting, not review, is the bottleneck. Consultant review typically takes 2 to 10 days. Time spent waiting between steps makes up most of the elapsed time, and in the worst bundles runs far longer than the review itself.
HLGA release against the 3-day standard
Steps after acceptance
30 bundles. On average 11 days from acceptance to the site tour, then 24 days to the observation.
How I report it
- Median and mean together. The median is the typical bundle, the mean shows what the tail costs.
- Every duration against its standard (3 days for HLGA, for example), so the gap is visible.
- Outliers handled one by one. A bundle at 600 days is a case to resolve, not an average to explain.
- Waiting time as its own measure, separate from review time, so each side can see what it owns.
These are pages from my Power BI dashboard. Bundle names and codes are blurred on every chart. Click a page to enlarge it.