Case 01 / Power BI

The Haram handover, day by day

I designed and built the Power BI dashboard that follows the handover work, from the first idea to the finished pages. It measures cycle times across the bundles against governance, and is reported to the Ministry of Finance as program owner.

Role
Concept, design and build
Build time
362 hours
Reported to
Ministry of Finance (program owner)
Scope
One building of the program; 22 to 79 bundles per measure
Tools
Power BI, Excel
My idea, built end to end

I saw where the time was going, and built the way to show it.

  1. 1
    The idea

    Measure every step of every bundle against its agreed duration, so the delays can be seen.

  2. 2
    The build

    I designed and built every page in Power BI myself: measures, charts and layout.

  3. 3
    The use

    The pages became the basis for reporting handover progress and delays to the Ministry of Finance.

Power BI / Bundles follow up
Bundles Follow Up. Weekly approvals and rejections, with page switches on the right.

The dashboard, page by page

Front pageNavigationTotalsSnag list

What changed

  • Shorter waits. Once every wait was visible, the time bundles spent waiting between steps came down.
  • Pressure from day one. We follow up with the contractor on a single day of delay, instead of discovering it weeks later.
  • Strong answers to claims. The dated record of every step lets us respond to the contractor's claims with evidence.
  • Better negotiation. When the contractor is the one running late, we negotiate with the numbers in hand.

Finding

Waiting, not review, is the bottleneck. Consultant review typically takes 2 to 10 days. Time spent waiting between steps makes up most of the elapsed time, and in the worst bundles runs far longer than the review itself.

HLGA release against the 3-day standard

6 daysMedian release time, against a 3-day standard
32 daysMean release time, pulled up by a long tail
11×2,263 days used across 70 bundles, against 210 at standard
Power BI / HLGA release period
HLGA release period. 70 bundles, days to issue against the 3-day standard. 31% on time or early, 69% later.

Steps after acceptance

Power BI
Site tour and site observation

30 bundles. On average 11 days from acceptance to the site tour, then 24 days to the observation.

Power BI / Acceptance period and revisions
Acceptance period and revisions. Days in acceptance for each bundle, drawn against the number of revision rounds it went through.
Power BI / Acceptance to report issue
Acceptance to report issue. Median 52 days, mean 95. A few bundles run far above the rest.
13 daysMedian acceptance to site visit, 79 bundles
30 daysMean for the same 79 bundles; total 2,336 days
4bundles above 300 days that distort the mean

How I report it

  • Median and mean together. The median is the typical bundle, the mean shows what the tail costs.
  • Every duration against its standard (3 days for HLGA, for example), so the gap is visible.
  • Outliers handled one by one. A bundle at 600 days is a case to resolve, not an average to explain.
  • Waiting time as its own measure, separate from review time, so each side can see what it owns.

These are pages from my Power BI dashboard. Bundle names and codes are blurred on every chart. Click a page to enlarge it.